Buildings.Controls.OBC.ASHRAE.G36.Plants.Chillers.MinimumFlowBypass.Validation
Collection of validation models
Information
This package contains validation models for the classes in Buildings.Controls.OBC.ASHRAE.G36.Plants.Chillers.MinimumFlowBypass.
Package Content
| Name | Description |
|---|---|
| Validate control of minimum bypass valve | |
| Validation sequence of specifying minimum bypass flow setpoint |
Buildings.Controls.OBC.ASHRAE.G36.Plants.Chillers.MinimumFlowBypass.Validation.Controller
Validate control of minimum bypass valve
Information
This example validates Buildings.Controls.OBC.ASHRAE.G36.Plants.Chillers.MinimumFlowBypass.Controller. It demonstrates the bypass valve control to maintain the minimum chilled water flow through the chillers.
-
From 0.1 seconds to 0.7 seconds, there is no chilled water pump proven on
(
uChiWatPum=false). Thus, the bypass valve position setpoint is 1. - From 0.7 seconds to the end, there is chilled water pump proven on. When the measured chilled water flow is less than the setpoint, the bypass valve position setpoint is 1. After the measured chilled water flow is greater than the setpoint, the bypass valve setpoint gradually decreases.
Modelica definition
Buildings.Controls.OBC.ASHRAE.G36.Plants.Chillers.MinimumFlowBypass.Validation.FlowSetpoint
Validation sequence of specifying minimum bypass flow setpoint
Information
This example validates Buildings.Controls.OBC.ASHRAE.G36.Plants.Chillers.MinimumFlowBypass.FlowSetpoint. It shows the calculation of the minimum chilled water flow through the operating chillers.
It includes three instances staUp, staDow,
and onOffStaUp that show the minimum chilled water flow
setpoint when the plant is staging up, staging down, and staging up
with one chiller being enabled and another chiller being disabled.
-
For instance
staUp, the plant stages up at moment 1 second, It stages up from chiller 1 and 2, to also enable chiller 3. When in the staging process, all the up devices have been controlleduUpsDevSta=trueat 1.2 seconds, the minimum flow setpoint changes from 0.01 m3/s (sum of minimum flow of chiller 1 and 2) to 0.015 m3/s (sum of the minimum flow of all chillers). The staging process takes 1.5 seconds (byPasSetTim). -
For instance
onOffStaUp, the plant stages up at moment 1 second. It enables chiller 3 and disables chiller 2. When in the staging process, all the up devices have been controlleduUpsDevSta=trueat 1.2 seconds, the minimum flow setpoint changes from 0.01 m3/s (sum of minimum flow of chiller 1 and 2) to 0.015 m3/s (sum of the minimum flow of all chillers) at 2.7 seconds. When the chiller staging process are done (uSubCha=true), the minimum flow setpoint changes back to 0.01 m3/s (sum of minimum flow of chiller 1 and 3). -
For instance
staDow, the plant stages down at moment 1 second. It stages down from chiller 1 and 2, to disable chiller 2. When in the staging process, all the up devices have been controlleduUpsDevSta=trueat 1.2 seconds, the minimum flow setpoint changes from 0.01 m3/s (sum of minimum flow of chiller 1 and 2) to 0.005 m3/s (the minimum flow of chiller 1). The staging process takes 1.5 seconds (byPasSetTim).